Please plan your travel accordingly, reduce speeds in construction areas and observe all signage – SAFETY FIRST.  Dates of work and projects are weather permitting and subject to change.

Current Project Updates

Updated July 19 / 2019


Project: Hampton Road – Almon Lane TO Rothesay Corner
Streets affected: Hampton Road – reduced to one lane with flaggers and/or traffic signals
Start: July 23, 2019 at 7:00 am
Duration: Approximately 3 weeks (weather permitting)
Description of work: Renewal of an existing watermain. Please observe all TRAFFIC CONTROL signage.


Project: Marr Road – Curb, sidewalk and asphalt Resurfacing
Streets affected:  Marr Road
Start: July 8, 2019 at 7:00 am
Duration: Approximately 6 weeks (weather permitting)
Description of work: Infrastructure spot repairs, curb and sidewalk reconstruction and asphalt resurfacing.  Traffic will be permitted FROM Hampton Road to Campbell Drive.  Traffic from Campbell Drive to Hampton Road WILL BE DETOURED via Campbell Drive or Grove Avenue.  Local traffic can access from Hampton Road ONLY.  Please observe all TRAFFIC DETOUR signage.


Project:  Drainage – Church Avenue
Streets affected:   Church Avenue
Start: July 2, 2019 at 7:00 am
Duration: Anticipated end date July 19, 2019 at 7:00 p.m.
Description of work: Underground infrastructure and road work will be taking place on Church Avenue between Peters Lane and Gondola Point Road. This portion of Church Avenue will be closed to through traffic.  There will be LOCAL TRAFFIC access ONLY.  Please observe all TRAFFIC DETOUR signage.  Work is expected to finish July 19, 2019.


Project:  Drainage – Church Avenue
Streets affected:  Station Road, Church Avenue and a portion of Gondola Point Road (from Clark Road to Rothesay corner)
Start: May 29, 2019 at 7:00 am
Duration: Anticipated end date June 28, 2019 at 7:00 p.m.
Description of work: Underground infrastructure and road work will be taking place at the intersection of Church Avenue and Gondola Point Road. Church Avenue will be closed to through traffic onto Gondola Point Road.  Gondola Point Road will be closed to through traffic between Clark Road and Rothesay corner.  There will be LOCAL TRAFFIC access ONLY.  Please observe all TRAFFIC DETOUR signage.  Work is expected to finish June 28, 2019.


Project:  Drainage – Church Avenue
Streets affected: Gondola Point Road and Church Avenue intersection
Start: May 21, 2019 at 7:00 am
Duration: Anticipated end date May 28, 2019 at 6:00 p.m.
Description of work: Gondola Point Road reduced to one lane of traffic at Church Avenue with flaggers in place during work hours (7:00am – 6:00pm). Two lanes of traffic to be restored during non-working hours. Motorists should expect significant delays during peak traffic hours (morning and evening rush).


 

Project: Drainage – Church Avenue
Streets affected
: Station Road / Church Avenue
Start: April 30 / 2019
Duration:
Direction: Eastbound / Westbound
Description of Work: Construction work on Station Road between Gondola Point Road and Station Road (northbound/southbound) requires complete closure of this section of street.  A detour has been set up via the opposite end of the Station Road loop beginning at the intersection of Gondola Point Road and Hampton Road. This closure is expected to remain in effect until approximately May 31.


2019 Capital Projects

Asphalt Resurfacing Microseal Placement Drainage
Allan Avenue Canwell Court Church Avenue
Chapel Road Hooper Drive
Marr Road Joelyn Lane Curb & Sidewalk
Ricketts Lane Kimberley Drive Marr Road
Mark Avenue
Olive Lane
Rodney Street
Sheryl Drive

 

Share this page:

Facebook Google Twitter Email